What to Expect While Retrofitting
Your Table Line With
 
 
 
 
 
 
 
 
 
 
 
What to Expect
Retrofit at MiTek
Retrofit at Truss Plant
Down-time
2 days for every 3 tables.
9-Table System=6 days
3 days for every 2 tables.
9-Table System=13-1/2 days
Number of people needed
Customer's preference
4
Electrical power
Must be supplied by local electrician
Must be supplied by local electrician
Work to be completed prior to shipping tables or MiTek rep arriving on-site
Un-install tables.
Remove lifters, air kit components, leveling bolts.
Number tables in order.
Remove wooden sub base if applicable.
Clean tables.
Ship to MiTek.
Pick up when complete.
Remove lifters.
Remove wooden sub base if applicable.
Clean tables.
Optional Services
Re-installing tables
none
 
 
 
 
 
 
 
 
 
 
 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 